Wessex Signal Post Renewals

April 2024 saw Amaro instructed to replace two signals on the Wessex Route, both of which posed a safety risk due to significant levels of deterioration.

  • Completed with zero lost time incidents
  • Completed ahead of programme
  • A risk to rail users and maintenance staff eliminated
  • Reliability and cost-efficiency improved

The challenge

Following a report that signals at both Dorchester South and New Malden were leaning away from the track, subsequent examinations of the structures’ foundations found evidence of crumbling and subsidence. As a result, these two signals (namely DR165 and W210) were scheduled for replacement to alleviate a pressing infrastructure safety issue.

The solution

Following a competitive tender process, Network Rail Wessex Works Delivery instructed Amaro to carry out the necessary design, procurement, installation, and testing of the following two signals:

  • DR165R – A right-hand mounted 2-aspect filament signal at Dorchester South on the BML2 ELR
  • W210 – A left-hand mounted 4-aspect Westinghouse filament signal on the Up Kingston at New Malden

… installing updated signal posts and replacing the end-of-life filament signals with cutting-edge Dorman LED units.

During a single 52-hour possession in April 2024, an Amaro team supported by a number of third-party organisations completed all works within 5 separate shifts, averaging approximately 9 hours per shift.

Shift one saw traffic management established, followed by the preparation and marking up of a number of screw pile hole locations, required to anchor the new signal posts securely in place.

With the RRV arriving at the work site towards the end of the first shift, the following shift focused on the installation of the screw piles themselves with shift three seeing the establishment of a new platform and hardstanding around the signal base, not to mention a modern GRP walkway and handrails.

With the preparatory works now complete, shift four saw the piling works finalised, followed by the installation of a lightweight, fold-down signal post and an upgraded LED signal unit. Along with all associated cabling, the location case was prepared ready for changeover before the now-redundant signal was recovered safely using the RRV.

During our final shift on site, a 6-strong team returned to Dorchester South to carry out pre-testing, performing a controlled changeover of cable before the new signal was sighted, tested and returned back to the signaller.

All works were carried out in accordance with W210 Signal Sighting Form (Appendix A) and the Wessex Signalling Equipment Policy NR/RAM/WSX/2014/001 v5 (Appendix C).

The outcome

Whilst the upgrade at New Malden is scheduled for much later in the year, works at Dorchester were completed safely, successfully, and 5 hours earlier than planned. Thanks to the dedication of Amaro and its partners, signal DR165R no longer poses a risk to maintenance staff and passengers and will provide a far more cost-effective and reliable service for years to come.

Wandsworth Road Signalling Upgrades

Wandsworth Road Signalling Upgrades

Advancements in technology, reliability, and energy efficiency – not to mention the need to reduce Network Rail’s maintenance burden – necessitated the upgrade of three filament-type signalling heads in and around the Wandsworth area. Linked to London’s wider multi-million-pound Victoria Resignalling Programme, these works saw the outdated units swapped out for cutting-edge LED replacements.

Victoria Cable Pulling

Cable Pulling – Phases 4 and 5, Victoria Area Re-Signalling Programme

First hitting site in August of 2022, Amaro was instructed to carry out all of the cable pulling associated with phases 4 and 5 of Network Rail’s Victoria Area Resignalling Programme (VARP) as part of a drive to boost asset reliability, improve passenger experiences and journey times, and reduce the ongoing maintenance burden upon the end client.

VIC 3 Cable Renewals

VIC 3 Cable Renewals

Forming part of Network Rail’s Minor Signalling Framework, in March 2023 Amaro hit site in Central and South London, tasked with replacing 13 end-of-life signalling power cables (12 x 48c and 1 x 37c) on a like-for-like basis in the area between Victoria station and Battersea Park